MLI Cutover Major Milestones & Activities
| Task | Day | Time (Eastern) | Time (Pacific) | Status |
| Begin Cutover Staffing Plan (War room Open) | Friday | |||
| Intellinet Environment - Daily Processing Completed | Friday | 9:15 PM | 6:15 PM | |
| Intellinet Environment Disabled - Begin to bring up RISC / SISC | Saturday | 6:05 AM | 3:05 AM | |
| RISC / SISC Active - ET Testing Completed | Saturday | 11:10 AM | 8:10 AM | |
| Begin AD / QA / Partner Testing | Saturday | 12:30 PM | 9:30 AM | |
|
Foresight - All Testing Completed |
Saturday | 4:15 PM | 1:15 PM | |
|
Irvine - All Testing Completed |
Saturday | 5:45 PM | 2:45 PM | |
|
LA & WDM - All Testing Completed |
Saturday | 7:00 PM | 4:00 PM | |
|
Declare Success |
Saturday | 7:30 PM | 4:30 PM | |
|
Week One Staffing Schedule To Begin |
Saturday | 8:00 PM | 5:00 PM |